Indicative maintenance schedule, H-Gas Storage BEB

The following schedule gives an overview of the mainte­nance work currently planned on BEB's gas storage system, with contract-relevant capacity reduc­tions.

The infor­mation will be contin­u­ously updated.

Planned mainte­nance measures with contract-relevant capacity reduction
StoragePeriod
06:00 - 06:00
Remarks
Dötlingen20.04.2010 - 03.10.2010 Injection Period, withdrawal capacity limited up to 50% (1)
Dötlingen04.10.2010 - 17.10.2010Mainte­nance, no operation of the storage facility (2)
Dötlingen18.10.2010 -
spring 2011
Withdrawal Period, injection capacity limited up to 50% (1)
Uelsen10.05.2010 - 17.10.2010 Injection Period, withdrawal capacity limited up to 50% (1)
Uelsen18.10.2010 - 31.10.2010Mainte­nance, no operation of the storage facility (2)
Uelsen01.11.2010 -
spring 2011
Withdrawal Period, injection capacity limited up to 50% (1)
Harsefeld20.09.2010 - 25.09.2010Mainte­nance, no operation of the storage facility (2)

Footnote:

  1. Nomina­tions will be accepted; customers will be informed of possible curtail­ments in agreed form
  2. Nomina­tions will not be accepted